Options Page of the Calculate Progress Wizard
Use this page to select the options that you want to use in calculating progress.
Contents
| Field | Description |
|---|---|
| Use adjusting entry to remove Progress for deleted budget | If earned value has already been calculated for a work package, then the entire budget is deleted. This option allows you to show a negative earned value in the current period to zero out the previously posted earned value. If this option is cleared, Cobra deletes the earned value for the resource without an adjusting entry when a budget is deleted. |
| Progress by: | You have four options for calculating earned value:
|
| Exclude Work Packages with the following Progress Techniques | Click |
| Calculate Assignment Percent Complete for apportioned Work Packages | Select this option to calculate progress on apportioned work packages using the Assignment % Complete progress technique. This option evaluates all budget classes with the Include in Budget option selected. When you select this option, Cobra will apply percent complete values from source resources to their corresponding apportioned resources based on the apportionment definitions in the assigned resource file. The calculation supports two scenarios:
If an apportioned resource has only one source, the source’s percent complete is directly applied. If there are multiple sources, Cobra calculates a weighted average based on BAC hours (or another applicable source result) before assigning the percent complete to the apportioned resource. Calculating Progress for Apportioned Resources The Calculate Progress for Apportioned Resources feature calculates the Assignment % Complete values for all apportioned resources. Once this is completed, the progress totals for those Assignment % Complete values are calculated based on the updated values. This process repeats for each level of apportionment if multiple levels are defined in the project. |
| Force SPI of apportionment resources to match the source SPI | Select this option to ensure that the earned value for apportionment items receives the same SPI as the base. Note: This option is disabled if the Calculated Apportionment progress technique is selected on the Exclude Work Packages with the following Progress Techniques option.
Note: This option is always disabled regardless of the progress technique if the Secure option on the Progress Preferences tab of the Project Properties dialog box for the project is selected.
|